About The Project
This project was initiated in 2006 to protect the town of Givet, situated in the Ardennes region of northern France. Since the devastating floods of December 1993 and 1995 the protection of the population and their assets has been a major concern for the municipality. This operation is part of a global €20-million project to combat flooding.
The last phase of works began in 2010 with preparatory ground work, earthworks, and tree felling, followed by instalation of sheet pile cutoffs, slabs, and concrete walls in readiness for installation of demountable aluminium flood barriers.
This 3km-long project covering a footprint of more than 2900m2 is the largest of its type ever carried out in France.
Programme Of Work
A special feature of this impressive project is that it involves demountable protection, as has been used by other towns in Europe (e.g. Bewdley in England and Cologne in Germany which holds the record for its 10km along the Rhine). The Meuse is a plains river.
Its flood rises slowly and gradually, generally after a long rainfall event, giving time to predict a flood and react by installing the defences as soon as the water is seen to start rising upstream. The installation time estimated by the Municipality of Givet is 48 hours (more than 650 posts to be bolted to bas plates and 3000m2 of aluminium boards to be slotted into place).
Demountable Protection During Assembly
The works were divided into a number of separate zones on the left and right banks of the Meuse. Three different types of flood defence are involved: fixed defences comprising walls of appropriate heights (0.9 to 3.2m); demountable defences between 1.2 and 1.3m high; and composite defences, comprising a wall combined with demoun able defences, between 1.1 and 3.1m high.
Read more
The height of the fixed defences (walls) is based on the level of the twenty-year flood and that of the demountable defences on the level of the one-hundred-year flood. Sheet piles are used to create underground cutoffs. They prevent seepage below ground level and take the hydraulic thrust along a large part of the length on the right bank and in places on the left bank. They also serve as foundations for the defensive walls.
Less
Read more
The height of the fixed defences (walls) is based on the level of the twenty-year flood and that of the demountable defences on the level of the one-hundred-year flood. Sheet piles are used to create underground cutoffs. They prevent seepage below ground level and take the hydraulic thrust along a large part of the length on the right bank and in places on the left bank. They also serve as foundations for the defensive walls.
Less
The soil investigations carried out generally showed that the top layer of loamy deposits is of poor quality. Deeper strata at between 4 and 7m made up of sand and clayey, sandy gravel have quite good geotechnical properties. Below 7m depth the subsoil is schist. The sheet piles were driven to depths of 4 to 5m and as deep as 7m in places, depending on the zone. They were driven with an ICE625B vibratory unit powered directly by the hydraulic circuit of the excavator. In the Quai de Rancennes area an ICE223 vibratory driver mounted on a KH150 (Hitachi) lattice-boom crane was used.
Reinforced-concrete coping beams were cast on top of the sheet pile walls and on top of these beams were built concrete walls with patterned colour-stained facings or Givet bluestone, depending on the zone. The baseplates and the slotted posts at the ends of sections of demountable defences were then fixed into the wall.
Read more
Behind the existing quaywall, a large concrete slabs was cast and serves as the foundation of the concrete wall.
A total of 850 tonnes of sheet piles, 750 baseplates, and 4000m3 of Givet bluestone masonry were used.
The works were completed in mid 2011. On September 14, 2011, trial erection of the demountable defences was faster than expected (less than 48 hours). The real test will take place when the next 100-year flood occurs.
Less
Read more
Behind the existing quaywall, a large concrete slabs was cast and serves as the foundation of the concrete wall.
A total of 850 tonnes of sheet piles, 750 baseplates, and 4000m3 of Givet bluestone masonry were used.
The works were completed in mid 2011. On September 14, 2011, trial erection of the demountable defences was faster than expected (less than 48 hours). The real test will take place when the next 100-year flood occurs.
Less
Date Of Completion
Behind the existing quaywall, a large concrete slabs was cast and serves as the foundation of the concrete wall.
A total of 850 tonnes of sheet piles, 750 baseplates, and 4000m3 of Givet bluestone masonry were used.
The works were completed in mid 2011. On September 14th, 2011, trial erection of the demountable defences was faster than expected (less than 48 hours). The real test will take place when the next 100-year flood occurs.
Flood defense
Givet | France
Design | Communauté de communes Ardennes Rive de Meuse |
Construction | Municipality of Givet |
Engineer | EGIS EAU - EGIS AMENAGEMENT - Mr WUSTNER consortium – Lead firm EGIS EAU |
Construction contractor | BOUYGUES TP Régions France – ESTHI consortium (Package No. 1: Flood barriers) |
Sheet piles | PU8R , PU9R, PU15R |
Length | 4 to 8m |
Steel grade | S 240GP to S 355GP |
Connectors | C9, C14 and Ω18 |
Total | 850 tonnes |